The China Machinery Engineering Corporation, managers of Phase 2 of Omotosho Power Plant in Ondo State, says it will complete the 500 mega watts plant by February. Mr Liu Zhao-Long, the Managing Director of the company, disclosed this to Newsmen in Lagos.
Zhao-Long said that three out of the four turbines were already functioning and that the fourth would be completed by February. “We have almost finished work at the Omotosho Phase 2. The three turbines are contributing 375 mega watts to the national grid. When the fourth turbine is completed by February, the management will observe the warranty period of a year to oversee the plant before officially handing it over to the government,’’ he said.
Zhao-Long commended the effort of the Federal Government towards ensuring the availability of stable electricity supply to Nigerians. The plant started in 2010.
-
Finance1 day agoCBN cuts 1-Year Treasury Bill rate, rejects Bids
-
News1 day agoCourt orders British Govt. to pay £420m to 21 coal miners killed by colonial masters
-
Economy1 day agoBPE, stakeholders unite to rollout $500m free meters, DisCos pledge to lead drive
-
Business1 day agoMTN to acquire controlling stake in IHS Holdings, eyes full ownership
-
Agriculture1 day agoOver 2.5m metric tonnes of food valued N2trn produced in 2yrs—FG
-
Maritime1 day agoNIMASA mulls expansion of deep blue project, calls for continued partnership with Navy
-
Oil and Gas1 day agoDangote refinery backs gantry loading, cautions against costly coastal evacuation
-
Economy10 hours agoDubai’s consumer electronics maker, Maser Group to invest $1.6bn in Nigeria, others

You must be logged in to post a comment Login